Pipe bridgePathRunway pose

Extension of the sewer system in the upper Valley of Astico

Pipe bridge

  • Year of completion:
    During construction
  • Municipality of Valdastico
    Comune di Pedemonte
    Municipality of Lastebasse
  • Client:
    AVS S.p.A.
  • Works amount:
    € 4,300,000

Description of work

Sewer line extension run grafting on line coming from the province of Trento and delivering downstream at the village of San Pietro Valdastico (VI).

Pipe laying

Professional performance

Joint assignment:

Preliminary draft

Final design

Executive project

Coordinating project security

Implementing security coordination

Construction management

Measurements and accounts

Drawing

The project in brief

Running a long stretch of sewer pipe Ø 10.00 km run with porcelain 400 mm. The path meets 15 crossings as well as underground bed crossing 1 planes, two pumping stations

Pala